LockDry Metal Decking Installation
1: Square & Fasten Starter
|
2: Fasten opposite side.
Starter & Finisher only. |
3: Fill 2" long bead in the channel against the structure. Prevents water backup.
|
4: Seal the top interlocking joint 2".
|
5: Interlock & wipe excess sealant.
|
6: Fasten & Repeat for the remainder.
|
7: For Stucco, Brick, etc. run a bead of sealant the entire length of seam.
|
8: Lapped sidings use standard flashing under the siding to the top surface of the decking. Seal between the flashing & decking.
|
9: Fasten the edge trim the outside.
|
10: Steps use a Starter & Finisher
|
ENJOY!
|